Why Europe Struggles to Unify Railway Signalling
Two decades after the first ERTMS specifications entered EU law, about a tenth of the TEN-T network is equipped. Why a standard every Member State signed up to is still hard to deploy - and what the 2023 CCS TSI revision changes.

By the end of 2024, ETCS covered roughly 10% of the TEN-T network, about 12 400 km, and was installed on 19% of the EU fleet, or 8 730 vehicles. The first ERTMS specifications entered EU law in 2002. The TEN-T Regulation (EU) 2024/1679 now requires ERTMS on the core network by 2030 and on the rest of the TEN-T network by 2050.
After more than two decades, only about one tenth of the network is equipped. The Third ERTMS Work Plan, published in February 2026, reports that deployment is uneven, slower than required, and at risk of missing the TEN-T objectives.
The real question is not whether Europe is late. It is why a standard every Member State signed up to is still so hard to put in place. The short answer: ETCS standardised the interface between train and track, not the railway behind it. And the railway cannot be shut down while it is being rebuilt.
The Cost of Fragmentation
Before ERTMS, almost every country ran its own automatic train protection system. Locomotives on international routes carried several systems, each with its own onboard equipment (source).
That legacy is still in place. ERA's list of CCS Class B systems names more than 30 distinct train protection systems still recognised across Europe: INDUSI, PZB 90, LZB, KVB, TVM, ASFA, ATB, TPWS/AWS, ALSN, EBICAB and SCMT, among others. It also lists legacy voice radio systems. The same document notes that two Member States using the same named system may still run incompatible versions.
The cost is substantial. The European Court of Auditors audited ERTMS in 2017. In the two Member States it examined in detail, trackside deployment averaged around €1.44 million per line-kilometre, while overall deployment stayed low. Every year of fragmentation means duplicated onboard equipment, border-specific operating rules, national approval work, and suppliers adapting the same product to each network.
The case for common signalling is clear. The hard part is introducing it into networks that were never designed as one system while keeping traffic running.
How Europe Built a Common Layer
Europe standardised only parts of the system. ERTMS defines a common train-control layer, ETCS for train protection and a radio layer for communication. The surrounding architecture is still largely determined nationally.
Three legal layers are often confused:
- Directive 2012/34/EU establishes the Single European Railway Area (SERA): market access, governance and charging. This is policy, not signalling.
- Directive (EU) 2016/797 governs interoperability and is the basis for Commission TSIs.
- The CCS TSI is currently Commission Implementing Regulation (EU) 2023/1695, dated 10 August 2023, as amended by Regulation (EU) 2026/693 of 19 March 2026. It is the binding technical specification for control-command and signalling.
ERA acts as the ERTMS System Authority. It maintains, monitors and manages the subsystem requirements, including the ETCS and radio specifications.
Standardising the train-facing protection layer is not the same as standardising the signalling architecture behind it. Interlockings, trackside assets, traffic management and Radio Block Centres were left largely to national practice. That is where much of the friction remains.
Common Specification, Different Railways
Two networks can be fully TSI-compliant and still be different railways.
The authorisation process shows why. An ETCS onboard unit can comply with the TSI and still not be accepted on a given network. It must demonstrate ETCS System Compatibility (ESC) and Radio System Compatibility (RSC) for its area of use, through checks defined by the relevant infrastructure manager. The CCS TSI makes this explicit. ERA publishes and maintains the list of ESC and RSC types in technical document TD/011REC1028. That document exists because TSI compliance alone is not enough.
There is also a generational spread. ERA's mandatory specification set for the CCS TSI is now ETCS Baseline 4 Release 1, alongside GSM-R and the first FRMCS specification. Yet Baseline 2 and Baseline 3 equipment remains in service on both sides of the interface and will do so for years. Infrastructure managers install new trackside while traffic keeps running. Operators run mixed fleets. Suppliers maintain products across several baselines and national configurations simultaneously.
The Commission lists the same practical problems:
- changing national deployment strategies
- shortage of skilled staff
- uncoordinated cross-border planning
- procurement processes that stall or fail
- technical issues from specification maturity to missing product documentation
A Specification That Keeps Moving
Signalling is exposed to technological uncertainty. A software platform can be replaced in a few years; a signalling installation has to work and remain maintainable for decades, alongside assets that are older still.
The 2023 CCS TSI shows how much is still in motion. The Commission's summary of the revision lists several changes:
- ETCS Level 2 with moving block, absorbing what used to be called Level 3. Level 3 never became a widespread deployment level on its own; the 2023 TSI merged it into Level 2 as an option for trains that can report their integrity.
- Onboard train integrity, the enabler for reducing trackside detection equipment.
- ATO up to GoA 2, targeting energy consumption and capacity.
- FRMCS readiness. GSM-R, the radio layer ERTMS depends on, is heading for obsolescence around 2030. FRMCS is its 5G-based successor. Infrastructure managers therefore have two migrations to plan.
- Braking curve model optimisation and a supervised manoeuvres mode replacing unsupervised shunting.
- Error-correction procedures and a single set of specifications, recognising that defects in the specification are themselves an interoperability problem, not just a supplier problem.
Hybrid Train Detection (HTD) sits alongside this. Developed by the ERTMS Users Group with ProRail and Network Rail, HTD combines ETCS train position and integrity reports with fewer trackside train detection devices. It is compatible with Baseline 4 without changing it, shortens headways and cuts trackside cost. For migration, it offers a direct step from Class B to HTD because onboard train integrity is not an access condition for the line.
The 2023 text did not settle things either. In March 2026, the Commission amended it again with Regulation (EU) 2026/693, less than three years after the original entered into force. The amendment added the test specifications needed to verify Baseline 4 trackside and onboard equipment, and ATO Baseline 1 equipment, against the 2023 rules. It also filled out two reduced system versions, 2.1 and 2.2, that the 2023 text had named but only fully specified for the most complete version, 3.0.
It also tightened the transition regime, because the 2023 provisions had been read differently in different places and were too narrow to protect contracts already under way from extra cost. And it extended infrastructure managers' existing ETCS System Compatibility continuation obligations to Radio System Compatibility, closing a gap the 2023 text had left open. The changes were large enough that the Commission replaced both annexes outright rather than patch them clause by clause. It is a small case study in its own right: a specification barely settles before the next correction round is due.
Each change has a case. Together they create a hard investment choice: deploy what is mature now, wait for what is coming, or build something that can absorb both. A system that is obsolete after one procurement cycle does not pay back on infrastructure with a multi-decade life.
Constraints You Cannot Design Away
There is no representative European train and no representative European route. Freight and passenger traffic share the same tracks. Trains differ in length, braking performance, speed and axle load. Platform lengths, gradients, tunnels and station throats limit what can be changed and when.
This has direct consequences for common rules. A braking or block design tuned for high-speed passenger traffic can waste capacity for a long, heavy freight train. An architecture that performs well on an open line behaves differently in a dense station area. A common system must balance safety, capacity and operational efficiency. Legacy equipment also usually has to remain interfaced throughout the migration.
The specification itself is another constraint. Requirements must be tight enough to remove ambiguity. When several suppliers implement safety-critical behaviour independently, a small difference in interpretation can surface years later as an incompatibility in the field. The error-correction procedures added in the 2023 TSI acknowledge this risk.
Compliance Is Not Approval
TSI compliance is necessary, not sufficient. Manufacturers and project organisations also work to CENELEC railway standards: EN 50126 for RAMS (reliability, availability, maintainability and safety), EN 50129 for safety-related electronic systems in signalling, and EN 50716:2023 for railway software. On top of these sit national rules, infrastructure manager rule books and operating procedures shaped by local infrastructure.
Safety evidence therefore does not transfer wholesale across a border. Interfaces, degraded modes and operational assumptions differ. Greenfield designs carry an extra burden: with no service history to draw on, every hazard has to be closed by analysis rather than by evidence.
What Is Actually Being Built Now
The work to standardise what sits behind the train-to-track interface is now under way.
EULYNX standardises the interfaces between the interlocking and trackside assets such as points, signals, level crossings and train detection. It also provides a reference architecture, model-based engineering methods and a test case catalogue. Its Baseline Set 4 Release 4 was published in June 2025, developed with the wider European CCS sector.
RCA (Reference CCS Architecture) started in 2018 as a joint initiative of the ERTMS Users Group and EULYNX. OCORA (Open CCS On-board Reference Architecture) followed from the railway undertakings' side. Both feed into the System Pillar of Europe's Rail Joint Undertaking (EU-Rail). The System Pillar develops a common operational concept and a functional, safe and secure system architecture, as well as specifications and standards for CCS, traffic management, digital automatic coupling and cybersecurity. Its mandate includes feeding these into TSIs and harmonised standards.
This matters to anyone specifying an RBC, an interlocking or a traffic management interface today. The target architecture is no longer speculative, and it is not limited to ETCS.
The same approach appears in Digital Automatic Coupling. The EU DAC Delivery Programme under EU-Rail is as much about coordination as coupler design. It brings together railway undertakings, infrastructure managers, wagon keepers, suppliers and maintenance bodies. That coordination is where much of the work lies.
What Progress Requires
Europe does not have to choose between permanent fragmentation and an overnight replacement that no one can fund or approve. The realistic path is to treat migration as a design problem in its own right.
In practice, that means five things:
- Start with interfaces that have the highest cross-border value, as EULYNX and the System Pillar are doing for trackside and onboard architecture.
- Design for coexistence. Legacy and target systems will share the network throughout the migration; HTD is an example of a step that works with existing trackside detection.
- Separate genuine local constraints from inherited habit. Gradients and platform lengths are real. Some rule book differences can be removed.
- Treat certification, operation and maintenance as design inputs. ESC/RSC demonstrations, safety cases and national approval effort are part of an architecture's cost, not paperwork added later.
- Keep specifications stable enough to invest against. Error correction and a single specification set help. So does resisting the urge to reopen settled interfaces.
None of this produces uniformity. The target is predictable, safe and financeable interoperability.
Tackling The Remaining Work
Europe has already shown that the hard part is possible. A binding common train protection standard now exists where dozens of incompatible national systems used to be the only option. What remains is making that foundation cheaper to deploy, faster to certify and useful across the full signalling stack: interlocking, RBC, traffic management and radio.
The remaining work rewards engineering that takes legacy seriously. Clean interface diagrams are easy. Migration paths that keep a network safe, available and approvable while it changes underneath are not. That is where much of the remaining cost sits.
Europe's railway is old, heterogeneous and never out of service. Anyone specifying signalling for it has to design for all three at once.
Abbreviations
- 5G = fifth-generation mobile network technology
- ALSN = automatic locomotive signalling, continuous
- ASFA = Anuncio de Señales y Frenado Automático (announcement of signals and automatic braking)
- ATB = Automatische TreinBeïnvloeding (automatic train control)
- ATO = automatic train operation
- AWS = automatic warning system
- CCS = control-command and signalling
- CENELEC = European Committee for Electrotechnical Standardization
- DAC = digital automatic coupling
- EBICAB = EBICAB train protection system name
- EN = European Standard
- ERA = European Union Agency for Railways
- ERTMS = European Rail Traffic Management System
- ESC / RSC = ETCS system compatibility / radio system compatibility
- ETCS = European Train Control System
- EU = European Union
- EU-Rail = Europe's Rail Joint Undertaking
- EULYNX = European initiative for standardising railway signalling interfaces
- FRMCS = Future Railway Mobile Communication System
- GSM-R = Global System for Mobile Communications – Railway
- GoA = grade of automation
- HTD = hybrid train detection
- INDUSI = Induktive Zugsicherung (inductive train protection)
- KVB = Contrôle de vitesse par balises (speed control by beacons)
- LZB = Linienzugbeeinflussung (continuous train control)
- OCORA = open CCS onboard reference architecture
- PZB = Punktförmige Zugbeeinflussung (intermittent train control)
- RAMS = reliability, availability, maintainability and safety
- RBC = radio block centre
- RCA = reference CCS architecture
- SCMT = Sistema di Controllo della Marcia del Treno (train movement control system)
- SERA = Single European Railway Area
- TEN-T = Trans-European Transport Network
- TPWS = train protection and warning system
- TSI = technical specification for interoperability
- TVM = Transmission Voie-Machine (track-to-train transmission)
- UIC = International Union of Railways
Sources
- Third ERTMS Work Plan: deployment status, February 2026 (European Commission)
- Commission Implementing Regulation (EU) 2023/1695: CCS TSI (EUR-Lex)
- Commission Implementing Regulation (EU) 2026/693: amending the CCS TSI as regards new testing specifications, a set of reduced specifications and transitional measures (EUR-Lex)
- Directive 2012/34/EU establishing a single European railway area (EUR-Lex)
- Trans-European Transport Network (TEN-T), Regulation (EU) 2024/1679 (European Commission)
- Preparing the future evolution of ERTMS: 2023 CCS TSI revision (European Commission)
- ETCS Levels and Modes (European Commission)
- What are the deployment challenges of ERTMS? (European Commission)
- History of ERTMS (European Commission)
- List of CCS Class B systems, ERA/TD/2011-11 (ERA)
- ERTMS Deployment Action Plan: ERA as ERTMS System Authority (ERA)
- ERTMS specification set, CCS TSI Appendix A (ERA)
- Special Report 13/2017: A single European rail traffic management system (European Court of Auditors)
- Hybrid Train Detection (ERTMS Users Group)
- EULYNX Baseline Set 4 Release 4 (EULYNX)
- System Pillar and European DAC Delivery Programme (Europe's Rail Joint Undertaking)
- FRMCS and GSM-R obsolescence (5GRAIL)
- EN 50716:2023, railway software (CENELEC, via standards catalogue)